Dear PP experts,
I have the following issues in Reduction of Operations in Reduction strategy and Reduction % in OPU3
1. I have created the Reduction strategy in OPJS with
a. 100 % reduction in queue time with Reduction level 6 with "Reduction of Transportation time (Move time)" indicator active
I have assigned this reduction strategy in OPL8 and in the operation in routing also
In OPU3 , I have assigned the "Maximum reduction level" - Reduce to reduction level 6 with reduction % as 40 % in 6th box
My routing details
Std Queue time is 6 days
Min queue time is 2 days
Std move time is 10 days
Min. move time is 3 days
My Production order dates are as follows,
Basic Order start date - 01.01.2014
Basic Order End date - 01.01.2014
Operation scheduled start date - 04.01.2014
Operation scheduled end date - 01.05.2014
As per SAP , the reduction strategy has to be applied and as per my Reduction strategy Queue time has to be reduced - 100 % and move time has to be completely reduced
But both Queue time and Move time is not getting reduced. Min. Queue time and Min. Move time is getting calculated in scheduling
I have created a production order Manually and through MRP also. No reduction is taking place
2. I am confused with the Reduction level % in OPU3 and OPJS? As given in SAP help, reduction level in OPU3 is for reducing the floats in Schedule margin key. I have updated the Reduction % in OPU3 for 40 % in 6th box , No reduction is taking place in floats also
Please clear whether my understanding towards reduction is correct
I have read SAP help and many threads in SCN before posting this thread
Please clear the above issues
Please do the needful
J. Bala