Hi experts,
When a new material will be launched, what is the best way to tune its BOM
1) Can we create a BOM with a USAGE different to 1 = Production?
2) Does this new BOM can be used in a routing?
3) Can we create a planned order without a previous BOM and we can assign the components when we are creating the planned order?
4) Can we create a production order without a previous BOM and we can assign the components when we are creating the production order?
At the end when the BOM is all right then we create a BOM with USAGE 1 = Production
Best regards,
Arnulfo Cordero Pradel